Town of Clarence — Planning Board
The Planning Board gave final development-plan approval to a three-storey, 50-unit building at 8750 Main Street, the last town vote before permits. It denied a 10-unit density increase on Transit Road at the developer’s own request, routing it to the Zoning Board. Also: a church lot split approved.
The project that began its trip through Clarence's boards in May 2025 reached the end of it in about ten minutes. 8750 Main Street Associates, LLC was before the Planning Board for development-plan approval of 50 multifamily units in a single three-storey building on the rear of the 9.6-acre Samuel’s Grande Manor property, in the Traditional Neighborhood District. The banquet hall at the front, which already contains apartments, stays.[1][2]
Director of Community Development Jonathan Bleuer declined to recount “a very lengthy history,” noting only that the town's engineering department had signed off this month on the technical plans. Attorney Sean Hopkins, for the applicant, filled in the milestones: a coordinated environmental review completed with the other agencies; a Town Board rezoning of the northernmost roughly 172 feet of the site and a special use permit; a Zoning Board variance for the third storey; and design work with this board's executive committee on what he called “more like a row house type project” with vertical and horizontal articulation “different than what I believe exists currently in Clarence.” The target is to break ground in early 2027.[1]
The one new issue came from the school district. Member Jason Geasling, leading the review, relayed a district concern about a nearby school playground and asked whether the applicant would put a four-foot fence along the rear property line. Hopkins said no, respectfully and at length: the playground is “several hundred feet back” from the property; a fence would enclose only one side and could be walked around; clearing vegetation for chain link would cost about $50,000 and, in his view, provide no benefit — and occupied buildings back there would be “actually safer” than the empty land is today. He offered instead to meet the district. The board accepted that; no fence condition was added.[1]
Geasling also put on the record that several architectural elevations were mislabelled (an elevation marked east is the south), and pressed on the rooftop mechanicals. A board member reminded Hopkins that in April the applicant had agreed to adjust screening after construction if units or vents remained visible from the road; Hopkins agreed he was “not trying to revisit the conditions.” No member of the public spoke.[1]
The approval carries 12 conditions, among them landscaping and fencing maintained and replaced in kind in perpetuity under the Landscape Committee's July 23 approval, dark-sky lighting with no freestanding fixture above 15 feet, screened mechanicals with vents painted to match, and open-space and recreation fees. Hopkins accepted them: “They are acceptable.” Next, the Chairman said, comes the meeting with the school — and building permits.[1]
The evening's second Hopkins application read as a defeat and was nothing of the kind. PB Investors, LLC holds an approval, dating to 2023, for a mixed-use project on about 10 vacant acres at 5695 and 5731 Transit Road, south of Highland Farms Drive: 22,810 square feet of commercial space and 84 apartments. It now wants 94. Three four-unit, two-storey townhome buildings would replace garages that were approved along the north side, near the Highland Farms homes; two units come out of the mixed-use building; the commercial space is unchanged.[1][2]
Why more units? Member Daniel Tytka asked directly, and Hopkins answered directly: construction costs have risen since 2023, a lender's commitment depends on the project penciling out, and “there's actually more money to be made from the townhomes than the garages. So it's really that simple.” He stressed that nothing moves closer to the neighbours to the north or east, and that the heavily wooded northeast corner stays untouched. A traffic letter from the applicant's engineer, requested by the state DOT, put the change at roughly one more trip per hour entering and three exiting at peak.[1]
Tytka's worry was parking, and a neighbour's customers. The plan provides 261 spaces where the code, counting each use separately, calls for slightly under 310 — about 47 short. Hopkins argued that commercial and residential demand peak at different hours, citing the developer's mixed-use projects at Main and Transit, which he said are “dramatically over-parked.” Tytka pointed out that those sites lack an overflowing neighbour: customers of the adjacent business already park in the mud on this vacant lot. Hopkins said that business has no parking rights on the property, and that the owner would enforce. “That's just my biggest concern,” Tytka said.[1]
One resident, Paul Wheeler of Kippen Drive, asked whether a stormwater area shown on an earlier slide had moved, worried that clearing for it would thin an already thin buffer. Hopkins said the stormwater system is largely unchanged and underground; the area at the back is bioretention required by the DEC, under a landscape plan already approved.[1]
The board then issued a SEQR negative declaration and denied the concept plan. The project has also not been built for a reason unrelated to density: it has sanitary sewer approval only for its first phase, and Hopkins said he hoped the long-awaited Peanut Line sewer project, now out to bid, would unlock the rest.[1]
The town's code allows no more residential density on this site than the 84 units already approved. The Planning Board cannot grant more on its own. The route to more runs through the Zoning Board of Appeals, which can grant a density variance — but only after the Planning Board has acted on the plan.
So the developer asked for exactly what he got: a negative declaration (no significant environmental impact) and a denial. As Tytka read into the record, if the Zoning Board grants the variance, the proposal “must return to the planning board” for concept review. A denial here is a procedural step, not a verdict on the townhomes.
Clarence Center United Methodist Church owns a 16.7-acre parcel at 9750 Clarence Center Road, at the corner of Herr Road, in the Residential Single-Family zone. It asked to split off a new, vacant 9.34-acre lot with about 655 feet of frontage, plus a sliver for a lot-line adjustment with the neighbouring 9850 Clarence Center Road. Bill Barber[*], of the church's administrative board, explained that the land, owned since the 1980s, had served as “kind of like an endowment” and now needed to become cash for a 30-year-old building. The church had planned to sell about half; “along came a buyer who said, I want the whole thing.” Two weeks. “Cash deal.”[1]
A neighbour across the corner, Carrie Van Horn[*] of 9700 Clarence Center Road, asked what would be built and why a realtor's sign had gone up before the town acted. Bleuer explained that the town does not prohibit speculative listings, but a lot cannot legally exist until the town approves it. Barber then read the deed restriction the church will attach: no two-family, multi-family or commercial use, single-family homes only. Under questioning, he confirmed that limits the type of housing, not the number of houses. Bleuer filled the gap: one house needs only a building permit; more than one would come back before this board — and under the minor-subdivision rules, a member established, the new parcel could be split only once more. Approved with five conditions, including county approval of driveway access and county health department review of any septic system.[1]
“That's always been green space,” Van Horn said. “I might not answer your concerns,” the Chairman told her, “but that's where it's at at this point in the process.”[1]
Present at roll call: Chairman Robert Sackett, 2nd Vice-Chair Wendy Salvati, Keith Lukowski, Daniel Tytka, Jason Geasling and Gregory Todaro. Vice-Chair Richard Bigler and member Jason Lahti were not called. Every motion was a roll call; no member voted no and no recusal occurred. Two roll calls are incompletely captured on the recording, as noted.
Per the Carmina Wood Morris Design plan dated April 2026 (final revision July 9, 2026) and Sutton Architecture drawings dated June 4, 2026. Conditions: engineering, building and fire requirements before site work; outside-agency permits; Landscape Committee approval of July 23, 2026 with landscaping and fencing maintained in perpetuity; closed dumpster enclosures; dark-sky lighting, nothing above the roofline, freestanding lights no higher than 15 feet; materials and colours as rendered; mechanicals screened and vents painted to match; site maintained in perpetuity; striped parking; curbing and traffic flow as approved; signage review; open-space, recreation and other fees.
Unlisted action; Part 1 EAF accepted, Parts 2 and 3 approved. Commercial and Restricted Business zones.
Denied because no residential density remains available under the code. Requested by the applicant as the prerequisite to seeking a density variance from the Zoning Board of Appeals; if granted, the plan returns to this board for concept review. Referred from the Town Board in June; SEQR review opened in July.
Unlisted action; one new lot in the Residential Single-Family zone.
Per the application received October 6, 2026. Conditions: Erie County DPW approval of access to the new lot; town building and engineering review of future construction; Erie County Health Department review of any on-site sanitary system; drainage easements filed if required before any building permit; open-space, recreation and other fees. The associated lot-line adjustment with 9850 Clarence Center Road is handled by the planning office, not this board.
September 16 approved 6–0. October 7 approved 4–0, with Tytka and Salvati abstaining because they were not present at that meeting.
What aired. The 6:30 p.m. work session on SEQR items and miscellaneous business is not streamed; the 7:00 p.m. meeting was recorded in full. The recording opens about a minute before the call to order.
Names. The board roster is human-verified against official minutes; the transcriber renders Tytka as “Taika,” “Tyco” and “Teichka,” Geasling as “Giesling,” Salvati as “Silvati” and “Salvani,” Lukowski once as “Wieckowski,” and Bleuer as “Bloor” and “Blair,” all mapped silently. Applicant entities, addresses and the Samuel’s Grande Manor name are taken from the agenda. Speakers named only on audio carry [*]. The applicant's traffic engineer, the developer and others present for PB Investors were named on the recording but play no part in this account and are not printed; nor are the neighbouring businesses discussed in the parking exchange, which are not parties to the application.
Votes. Two roll calls are incompletely captured: Todaro's response on the PB Investors negative declaration and the Chairman's on the 8750 Main approval are absent from the transcript. Both motions carried and no member is heard voting no. The minutes are the authority.
Checks run. Street names in the transcript validated against the town's street index without correction; the transcript's “Her Road” is the index's Herr Road. The three sites were checked against this publication's scanner address database: 8750 Main Street and the Transit Road parcels have no history; 9750 Clarence Center Road has a single fire-company call in October, unrelated to this matter and not reported.